COMMERCIAL FLOORING · OAKVILLE
3,000 Sq. Ft. Kindergarten Flooring Completed in 24 Hours
Strataline installed approximately 3,000 sq. ft. of LVT flooring over one weekend, working through the night so this Oakville childcare facility could reopen with zero downtime.
- Location
- Oakville, Ontario
- Facility
- Kindergarten / childcare facility
- Area
- Approximately 3,000 sq. ft.
- Work
- LVT flooring installation
- Schedule
- Weekend work through the night
- Turnaround
- 24 hours
- Operations
- Zero downtime for normal childcare operations
- Dust control
- Festool dust extractors and ZipWall dust barriers
- PLANNING WORK AROUND OPERATING HOURS?
Project overview
3,000 sq. ft. of LVT in one weekend
We had one weekend to install approximately 3,000 square feet of luxury vinyl tile at this Oakville kindergarten. Working through the night kept the job within 24 hours, with no interruption to normal childcare hours.
The challenge
Working around the kindergarten schedule
Furniture and learning materials were moved together to clear each work area. We worked through the classrooms and corridor, then reset the rooms before reopening.
Dust control and containment
Containing dust inside an active facility
Festool dust extractors and ZipWall barriers helped contain dust while work moved between rooms.
Before
Preparing an active classroom
Storage units, displays and play areas filled the classrooms. Moving their contents exposed the pale original floor and gave us access to the room edges.
Preparation and installation
Working through rooms and doorways
Dark wood-look LVT was laid across the classrooms and through the doorways into the corridor.
Overnight and weekend execution
The overnight push
Installation continued through the night, with the remaining classroom areas finished before furniture was put back.
Finished result
One continuous floor through the facility
The same wood-look flooring now runs through the classrooms and along the corridor.
Before and after
From pale flooring to dark wood-look LVT
The original classroom had pale flooring around its learning zones and storage. After installation, the room was reset over a continuous dark wood-look LVT surface.
Ready to reopen
Back in operation after 24 hours
Tables, storage and play areas were back in place after the 24-hour turnaround. The kindergarten reopened on schedule with zero downtime for normal operations.
FINISHED PROJECT
Finished classrooms and corridor
CONTINUE EXPLORING
Related projects, guidance and services.
Complete condo interior renovation before move-in
How We Turned an Eighties Newmarket Condo Into a Move-In-Ready Home
See a dated Newmarket condo renewed before move-in with smooth ceilings, new flooring, trim, doors, paint and coordinated condo logistics.
Connected staircase, railing, ceiling and flooring renovation
Opening Up an Oakville Home With a New Railing, Smooth Ceilings and Coordinated Floors
See how Strataline opened up an Oakville interior with a custom stair railing, hardwood and tile flooring, smooth ceilings and 20-foot popcorn ceiling removal.
Connected ceiling, hardwood flooring, staircase and painting renovation
Coordinating Smooth Ceilings, Hardwood Floors and a Curved Staircase
See how Strataline coordinated popcorn ceiling removal, smooth ceiling finishing, hardwood installation and a complete stair transformation under one dust-controlled renovation.
Should You Refinish Stairs or Install Hardwood Tread Caps?
Learn when existing hardwood stairs can be refinished and when carpeted or damaged stairs are better suited to hardwood tread caps.
Need renovation work completed around operating hours?
Strataline plans commercial flooring and interior renovations around active-facility schedules across Oakville and the Greater Toronto Area.